DOT

Merritt Pkwy Project to Close Ramps Wednesday, April 26, Greenwich to New Canaan

Download PDF

The Connecticut Department of Transportation is announcing that construction will be resuming on Route 15 (Merritt Parkway) in Stamford and New Canaan from the Greenwich town line just north of Exit 31, North Street, to the vicinity of Exit 37, Route 124 (South Avenue) beginning on Monday, April 17, 2017. 

The project consists of 6.5 miles of roadway resurfacing, safety improvements, and landscaping enhancements.  The work also includes rehabilitation of five historic bridges over Route 15. ____________

— an announcement from the Connecticut Department of Transportation

____________

Department of Transportation Project No. 0135-0270 was awarded to O&G Industries at a cost of $53,031,742.62 on July 23. 2013 and is scheduled to be completed by July, 2017. LANE CLOSURE AND DETOUR INFO

The following nighttime periodic closures of the northbound and southbound on/off ramps at Exits 34, 35, 36, and 37 on or about Wednesday, April 26 for joint sealing in the City of Stamford and Town of New Canaan will be required.

DOT

From Greenwich to Westport, Highway Lane Closures Day & Night Starting Monday, Dec 5

Download PDF

Nighttime highway work is already closing lanes on Interstate 95 at various spots between Greenwich and Westport, and for the week starting Monday, Dec. 5 more is on the way for daytime hours, both on I-95 and the Merritt Parkway, state officials have announced. Bottom line: In the area surrounding Darien and well beyond it, if you’re driving after 9 p.m. or before 5 p.m., plan for delays on Interstate 95 through Dec. 16. If you’re driving between 9 a.m. and 2 p.m. on either I-95 or the Merritt, expect delays.

DOT

Construction to Close Lanes on Merritt Parkway From Exits 31 to 37, Greenwich to New Canaan

Download PDF

The Connecticut Department of Transportation is announcing the resumption of construction activity on Route 15, the Merritt Parkway, in Stamford and New Canaan from the Greenwich town line just north of Exit 31 (North Street) to the vicinity of Exit 37 (Route 124 / South Avenue). Traffic will be shifted on Route 15 southbound and northbound near the area south of Newfield Avenue Bridge. ___________

— This is an announcement from the Connecticut Department of Transportation. ___________

The project began in August 2013 and consists of 6.5 miles of roadway resurfacing, safety improvements, and landscaping enhancements.  The work also includes rehabilitation of five historic bridges that cross over Route 15. The bridges are Bridge 00712, Route 124 (South Avenue); Bridge 00710R, Metro North Railroad; Bridge 00708, Ponus Ridge; Bridge 00702, River Bank Road; Bridge 00700 Guinea Road.

DOT

Nighttime Lane Closures on Merritt Parkway in Westport Thru Sept 2

Download PDF

Nighttime work has restarted on replacing the North Avenue Bridge over the Merritt Parkway in Westport, resulting in lane closures at night about a mile east of Exit 42, the Connecticut Department of Transportation has announced. The work on the highway, which is U.S. Route 15, is expected to continue for months, ending by Sept. 2, the Friday before Labor Day. The department also announced that flashing signs on Interstate 95, U.S. Routes 15, 7 and various state roads will be replaced at night starting in April, resulting in other nighttime lane closures. (See the bottom of this article for that announcement.)

Here’s the department’s announcement:

PROJECT UPDATE – Rehabilitation of Bridge Number 00732, North Ave over the Merritt Parkway (Route 15) in Westport

The Connecticut Department of Transportation is announcing that night work on the Merritt Parkway for the rehabilitation of the North Avenue Bridge over the Merritt Parkway in Westport has resumed.