Here’s the list of this summer’s road paving projects in Darien, as announced Friday by the town Department of Public Works:
![Darien road paving schedule 2019](https://darienite.com/wp-content/uploads/2019/06/Screen-Shot-2019-06-28-at-3.11.18-PM.png)
Image from Darien DPW
2019 Darien road paving schedule
Preparatory work will precede paving on all of the above roads. Dates listed above include milling and paving.
Road surfaces will have raised structures during these dates. Please avoid these roads if possible during these times or use extra caution if you must travel on these roads.
![Paving Repaving DPW Roads 7-29-16](https://darienite.com/wp-content/uploads/2016/07/Screen-Shot-2016-07-29-at-8.17.36-AM.png)
Sign at the intersection of Hollow Tree Ridge Road and Linden Avenue.
The above schedule is based on favorable weather conditions. Emergency access will be available at all times. Town of Darien police officers will be present to direct traffic and assist area residents during construction.
Driveway access will be limited during paving operations. However, no single driveway should be closed for more than an hour.
On street parking will be suspended during paving operations. Minor traffic delays are likely.
Please plan your travels accordingly.
Please call the Department of Public Works at 656-7346 for further information